A fabricator can send the same set of plans to two detailers and get very different prices. One bidder may allow for two phased releases and CNC files. Another may price a single PDF submittal. Give both bidders the same written scope and ask them to list their assumptions alongside their price.
Start with the drawing register
Send the sheets and addenda that define the work. List each document’s number, revision and issue date. Identify which drawings are current and which are background material. If an architectural revision changes an opening while the structural set still shows the old condition, flag the discrepancy for clarification.
A model can help the bidder understand the geometry. State its file format, revision and intended use. Tell the bidder which contract documents govern and who will answer questions about conflicts.
Put the boundaries in writing
Name the buildings, levels, grids or sequences included. List miscellaneous metals, stairs, rails, embeds and delegated design separately where they apply. For each item, say who supplies the design input and who prepares the drawings. Ask bidders to state exclusions explicitly.
For example, “detail the structural framing on grids A–D” leaves a question about a stair at grid D. Adding “stair and rail package by others; include framing supporting the landing” gives both bidders a comparable boundary. This is an illustrative scope, not a project specification.
List what the shop needs back
| Deliverable | What to specify in the RFQ |
|---|---|
| Shop and assembly sheets | Sheet format, title block, mark convention and a reference sheet the shop may share. |
| Erection drawings | Required plans, sections, piece marks and how packages should follow the erection sequence. |
| Material lists | Whether the shop needs preliminary procurement quantities, a release-specific bill of materials or both. |
| Machine files and models | Shop-approved format, units, model version and the person who will check a sample export. |
Identify the governing standards, editions and submittal requirements specified in your project contract documents. Include them with the RFQ so bidders can identify any related scope assumptions.
Ask each bidder to identify which outputs are included in the base quote and which carry an additional charge. A PDF sample can confirm layout; for a machine-data requirement, arrange a separate sample-file check with the shop.
Separate approval dates from shop-release dates
Work backward from the first material order or fabrication slot. Give dates for the first submittal, the expected review window and the first approved release. Identify who receives RFIs, who returns consolidated comments and how the shop learns a drawing has been superseded.
AISC’s historical Scheduling and Estimating teaching module, Section 2.6, treats drawing preparation and approval as separate schedule activities. Use that distinction when describing milestones; the project contract determines its review requirements.
Ask how many review cycles the quote includes and how the detailer handles a changed design after a release. A review comment and a revised design can create different amounts of work. Agree on the distinction while comparing proposals.
Compare two illustrative scope summaries
Suppose two bidders received the same drawing register, but their proposals describe the work below. Both summaries are fictional. The allowances illustrate what to clarify; they are not typical prices, standard inclusions or offers from Total Engineering Consultants LLC.
On a small screen, scroll the comparison horizontally to see the clarification column.
| Compare | Sample A | Sample B | Ask both bidders |
|---|---|---|---|
| Included steel | Main frame only; stairs by others. | Main frame and stair framing. | List the required stair work and its boundaries separately, then confirm the same inclusions and exclusions. |
| Output files | Shop and erection PDFs. | PDFs, a bill of materials and an NC export. | Define the base outputs and optional files. Confirm the receiving shop's format and sample-file check. |
| Release packages | One complete package. | Two packages split by area. | Name the required areas and submittal/release milestones so both proposals cover the same sequence. |
| Review allowance | One consolidated comment round. | Review allowance not stated. | Confirm included review rounds and the person responsible for consolidating comments. |
| Design changes | Changed-design work priced after scope agreement. | Change process not stated. | Ask how changed work is identified, authorized and priced before it proceeds. |
A blank allowance is an open question. It does not prove that work is included or excluded. Ask each bidder to restate the same required scope, keep optional items separate and record unresolved assumptions. Then compare the revised totals and schedule commitments. This also creates a useful starting scope for the fabrication drawing services enquiry.
Copy this project brief
Project / location:
Latest drawing register and addenda:
Included buildings, grids or sequences:
Excluded items / work by others:
Shop, erection, model and machine-file deliverables:
Shop standards or sample sheet available:
First approval submittal / review window:
First shop release / subsequent phases:
RFI contact and revision process:
Please identify assumptions, exclusions and optional costs.
Start with the fields you know. Mark outstanding items as open and ask the supplier to explain how each assumption affects the quote. When the proposals come back, compare the first release date, deliverables, exclusions and change terms on one sheet before comparing the totals.